Description 
    The project consisted of infrastructure work along the track bed platform where railway lines L124 and L26 intersect. Several bridge decks were renovated and noise barriers installed, including 2,000 m² of green walls. For the Moensberg station at Uccle, new platforms have been built. Simultaneous with these main works diverse road, bedding, demolition, earth- and sewerage works were performed.
Some figures:
- Earthworks: 50,500 m³.
- Steel delivered: 680 tonnes.
- Concrete TPG: 8,800 m³.
location 
    Project Details
                        Contractor                    
                    
                Horzelstraat 300, Ukkel, Brussels, Belgium
                     
                    Client 
    Infrabel
      Engineering Office 
    TUC Rail
      Construction period
3 years 5 months
Start work
01-2011
End of work
06-2014
 
                    







 
                                       