FH stretch project: expansion of BTB and BTQ buildings.

  • BTB building: demolition of existing building, renovation and construction of new hall: 50 m x 60 m with finishing
  • BTQ building: demolition of existing wall, renovation and construction of new hall + canopy: 200 m x 40 m
  • Infrastructure work: demolition and modification works, earthworks, sewers, foundations and pavements
  • Building expansion: foundations and floors, concrete works, columns, prestressed beams and vaulting, steel work and brickwork, façade work, joinery and roofing work
  • Finishing of floors and walls.

Willemen Construct came into being on 1 July 2018 as a result of the merger between Willemen General Contractor and the construction department of Kumpen.

 
location 

Project Details

Contractor
Smalleheerweg 31, Oostakker, Oost-Vlaanderen, Belgium
Client 
Volvo Europa Truck
Architects 
Grontmij
Engineering Office 
Grontmij
Construction period
6 months
Start work
04-2010
End of work
10-2010