Willemen Bouw was established on 30 April 2025 through the merger of Willemen Construct, Cosimco, Franki Construct and Tools.

Ecole de l'Ouest - Lodelinsart
    
         Demolition and reconstruction of the 'Ecole...
IFAPME Training Center - Perwez
    
         Construction of a training center in Perwez...
KdG Hogeschool Campus Zuid - Antwerp
Description 
    Campus Zuid of the Karel de Grote Hogeschool is the new home for 5,500 students. In addition to a new building, a former factory building was also transformed into office space, classrooms, or practical training rooms. The campus also includes a media library, a bookstore, underground bicycle storage space for 1,000 bicycles, and a parking garage. A central courtyard allows light and air into the whole project. Sustainability is central and is translated in the flexible use of space, smart LED lighting, self-regulating awnings, green roofs, solar panels, and a night cooling system. The campus also has a unique catering and cafeteria concept that encourages culinary innovation and local entrepreneurship.
Â
News
23/09/2016 - 18:30
  01/06/2015 - 15:30
  21/05/2015 - 14:00
  13/11/2014 - 14:00
  location 
    Project Details
                        Contractor                    
                    
                Brusselstraat 45, Antwerpen, Antwerpen, Belgium
                     
                    Client 
    Karel de Grote-Hogeschool
      Price 
    €38.000.000
      Architects 
    RAU
         Stramien
      Temporary partnership 
    Willemen General Contractor, Van Laere
      Surface area above ground 
    28 000m²
      Surface area subterranean 
    7 000m²
      Construction period
2 years 1 month
Start work
08-2014
End of work
09-2016
 
                    





























 
                                       